    Phase 6: Timeline

    Build Timeline Planner

    Map your build process, manage deadlines, and avoid delays. Adjust for weather, local crew availability, and permitting lead times in your county.

    6 to 12 weeks
    Design to Permit
    4 to 8 weeks
    Slab to Shell
    3 to 5 days
    Shell Assembly
    6 to 12 Months Out

    Design & Engineering

    Design package ($9,750)
    Includes a Walk Your Plans visit to walk your full-size floor plan and make final changes. Apply to start your project.
    Floor plan finalized
    Review and approve your final design before engineering begins.
    Engineering drawings completed
    Full set of structural, architectural, and foundation drawings from American Iron or VR Home Design, engineering stamps coordinated when your county or lender requires them.
    Permit application submitted (if required)
    Submit to your county or municipality with complete drawing package.
    3 to 6 Months Out

    Permit & Land Prep

    Permit approval received
    County review timelines vary, plan 2 to 8 weeks for most Missouri counties with active P&Z.
    Site prep crew engaged and scheduled
    Book clearing, grading, and excavation contractors early. Spring crews fill up fast.
    Utility connections planned and quoted
    Get electric extension quotes and confirm well/septic plans during this window.
    Concrete contractor selected and scheduled
    Book your concrete crew at least 6 to 8 weeks out in peak spring/summer season.
    4 to 8 Weeks Out

    Site Prep & Slab

    Site clearing and grading complete
    Building pad ready, compacted, and free of organic material.
    Utility rough-in under slab complete
    All plumbing stubs, electrical conduit, and utility rough-ins placed before pour.
    Slab poured and curing
    Concrete slab poured and beginning 28-day cure period. Don't rush; a proper cure is essential.
    Final SIP measurements confirmed against as-built slab
    DreamStart verifies foundation dimensions against panel order before fabrication is finalized.
    0 to 30 Days Out

    Shell Installation

    Slab is fully cured (28 days minimum)
    Concrete reaches full design strength at 28 days. Don't set panels on fresh concrete.
    Panel delivery staged on-site
    SIP panels delivered by flatbed semi. Coordinate delivery timing with local GC crew arrival.
    Wall panels erected (1 to 2 days)
    Solid-Core SIP wall panels installed on slab. Open spans, no interior bearing walls needed.
    Roof panels or trusses installed (1 to 3 days)
    Roof system set on top of wall panels. The local builder handles the complete roof-to-wall connection.
    Windows, doors, and exterior metal installed
    Shell is now weather-tight, a dried-in, locked building ready for interior finishes.

    What Causes the Most Delays

    • ! Permit delays (county reviews can run 3 to 8 weeks in active P&Z counties)
    • ! Concrete crew scheduling in spring/summer (book 6 to 8 weeks ahead)
    • ! Site not ready when crew arrives (see site prep checklist)
    • ! Utility delays, electric extension permitting can take 6 to 12 weeks
    • ✓ SIP shell installation itself is almost never the bottleneck; it's the fastest phase

    Missouri Seasonal Build Windows

    Best
    Spring (Apr–Jun)
    Best overall. Mild temps, good curing conditions. Book concrete early; this is peak demand.
    Manageable
    Summer (Jul–Aug)
    Possible but hot. Concrete needs special additives in 90°F+ heat. Crew demand is high.
    Excellent
    Fall (Sep–Oct)
    Excellent window. Good temps, lower crew demand. Target early fall to beat winter risks.
    Difficult
    Winter (Nov–Mar)
    Cold weather slows curing. Heating blankets required. Possible but adds cost and risk.

    Timeline Questions

    Start Your Timeline Today

    The $9,750 design package includes a Walk Your Plans visit to walk your full-size floor plan and make final changes. Get your price, then apply to start. The plans are yours to keep, even if you build elsewhere.