Site Prep Checklist
Use this checklist to confirm your site is truly ready before your slab is poured. your local GC crew can't start until the site passes these checks. Skipping any item adds weeks to your timeline.
Grading & Clearing
Utilities & Rough-In
Survey & Marking
Access & Staging
Typical Site Prep Cost Ranges (Missouri)
Ranges vary by location, access, and site conditions. Get 2 to 3 local bids.
The Most Common Delay We See
Concrete crews show up and can't pour because utility trenches weren't staked, or equipment can't access the pad. This pushes the slab 2 to 3 weeks and delays the shell behind it. Run through this list the week before your concrete pour, not the day of.
Site Prep Questions
See What Your Shell Costs
Once your site, panels and builder are in place, your shell can go up in 3 to 5 days. Get your instant price.
Related Reading
Barndominium Site Prep: What Needs to Happen Before the Slab
Clearing, grading, utilities, and pad prep: everything that must be done before concrete day.
FoundationWhy No Basements? The Slab-on-Grade Advantage for Barndominiums
Why slab foundations work better than basements for SIP barndominium builds in Missouri.
UtilitiesBarndominium Well Water Guide for Missouri Builders
Rural water planning: well depth, pump sizing, and connection timing for your build.